"Tomskneftekhim" Planned stopping repairs

A large block of works at the site is made in the framework of the project to expand production of polymers. In particular, in the production of polyethylene was repaired compressors, sections of the reactor block, extrusion and heat exchange equipment, cleaning separators, high and low pressure.

“During the repair and installation of pipelines made of individual pieces of equipment, carried out preparatory work for the connection of the upgraded equipment, made a unique work of ultra-high pressure pipe welding,” – said the director of the production of “Tomskneftekhim” Andrew Kugaevsky.
The repair work involved about 700 employees and 170 contractors’ workers playground.

In addition, during the repair process equipment replaced in the production of polypropylene, introduced modern process control system in the production of monomers